The Deck Professor

Lessons / Site and permits

Change it

Locate buried lines before digging

Lay out the footings clear of what is buried
HouseMeterPosts 5 ft
Show a hint

A footing hole laid out on top of the gas line.

Every number here is a working estimate. Check it with your building authority.Turn JavaScript on to work the lesson. The drawing shows how it starts.

The rule this lesson teaches

Get buried lines marked first; a deck over a gas line is vented on two sides and the meter stays reachable.

Read the answer

Words in this lesson