Put up this manufactured guard with what the permit needs behind it
Guard 36 inDeck 42 inGlass panel
Show a hint

A glass guard with no report behind it.

Every number here is a working estimate. Check it with your building authority.Turn JavaScript on to work the lesson. The drawing shows how it starts.

The rule this lesson teaches

A manufactured guard needs a CCMC report, a test report or stamped drawings, and is installed exactly as they say.